Board of Supervisors Approve $1.6 Million to Repair Venice Beach

1
409

From NBC:

The Board of Supervisors agreed Tuesday to spend $1.6 million to move sand at Venice Beach to repair erosion and shore up the coast.

Department of Public Works employees will move about 30,000 cubic yards of dry sand that has blown inland, north of the Venice breakwater, to an area about a half-mile south, where significant erosion occurred during winter storms from December 2004 to February 2005.

Venice Beach Breakwater

The breakwater has kept the ocean’s natural wave action from replenishing the beach near lifeguard headquarters in Venice.

The move will “provide a buffer to protect inland structures from coastal storm flooding and damage,” according to William Fujioka, the county’s chief executive officer.

Funding for the project come from vehicle license fees.

Construction is expected to begin in November and to take about six to eight weeks to complete.

Join the existing discussion on this in the forums by clicking here.

SHARE

1 COMMENT

Comments are closed.